    Originally planned for 4 units, this developed was challenged with a handful of passionate objectors. However, we worked with council and devised an equally viable 3-unit solution on this corner block. A combination of 2- and 3-bedroom units within 5-minute walk of Springvale train station and activity centre. The springvale demographic has evolved into a lively and more sophisticated area and therefore we ensured every fixture and fitting was above market specifications. Although only a 3-unit development we expect the finishing to be our best yet.

    Development Timeline

    Planning & Design

    February 2012 – Done

    Permit Approved

    August 2015 – Done

    Construction Commenced

    February 2020 – Done

    Construction Stage 1

    Base: March 2020 – Done

    Construction Stage 2

    Frame: May 2020 – Done

    Construction Stage 3

    Lock Up: July 2020 – Done

    Construction Stage 4

    Fixing – In Progress

    Construction Completed

    December 2020

    Leasing

    December 2020

    [bold_timeline_item_button title=”Expand” style=”” shape=”” color=”” size=”inline” url=”#” el_class=”bold_timeline_group_button”]
    Builder

    Westurban Construction

    Architect (Town Planning)

    Valente & Associates

    Architect (Working Drawings)

    Parallel Workshop Architect

    Current Status

    August 2020 - Lock Up stage completed. Plasterboard is up and all fixtures & fittings are being installed.

    Expected completion date

    November 2020